Sheppy Bomb

Case Histories (Investigation)

Zetica has undertaken UXO investigations at numerous sites on behalf of clients with a wide risk tolerance range.

Using innovative and pragmatic solutions to manage the UXO risk, ZeticaUXO’s involvement will typically reduce a client’s programme time and costs with respect to UXO hazards. A small selection of examples of our typical work is given below.

FROM PRE-DESK STUDY ASSESSMENT TO UXO CLEARANCE

Zetica was asked to provide UXO services for a road development scheme in the New Forest National Park.  As a first step, we undertook a pre-desk study assessment to determine whether a source of UXO hazard may be present on the site.

Although the area in question was not heavily bombed, records indicated that the New Forest had a long history of use for military training.  It was considered that the area may have been requisitioned during WWI or WWII and therefore a detailed desk study was recommended to properly understand the potential hazard.

Zetica’s detailed desk study confirmed that land encompassing the site had been used for military training activities during WWII, involving infantry and artillery units.  Through the use of aerial photography, we were able to identify potential impact areas where the probability of encountering UXO was likely to be higher and existing roads where it was concluded that UXO could not have been left unnoticed.  As such we were able to confidently zone the site as a low to moderate risk.

In the moderate risk areas, Zetica was asked to undertake a non-intrusive UXO detection survey and target investigation to mitigate the UXO risk on the site. A number of potential UXO targets were identified and on investigation, 1No. 20mm cannon shell was found and disposed of.

The target investigation confirmed the findings of Zetica’s desk study and, with confirmation of excellent detectability of UXO, we were able to reassure the client that the remaining UXO risk on the site was low.

Uxo

Military Activity

Survey

51824 06 Prior To Dem[1]

 

 

FROM RISK ASSESSMENT TO BOMB DISPOSAL

Bowers

Investigation Case Histories 3

ZeticaUXO was asked to undertake a detailed desk study in order to assess the potential UXO hazard for a 255ha area of land in the Thames Estuary.

Our UXO desk study and risk assessment identified that some areas of the site had a high probability that UXO could be present.

Of particular note was the potential for a large unexploded bomb (UXB) be present. A series of bombing raids had occurred during which that one bomb did not explode. Records indicated that efforts at the time to locate the UXB had failed despite several attempts.

In order to confirm the findings of our UXO desk study and risk assessment, we undertook a non-intrusive geophysical survey in order to try and locate the UXB, which was anticipated as being within a proposed excavation area.

The 255ha site was surveyed using ZeticaUXO’s TOAD system.  The survey was completed in 6 weeks with a number of significant targets being identified.  We also characterized geophysical noise across the site in order to zone areas where UXO detectability was less than anticipated.

Given the identified hazard from the UXO desk study research, Zetica was asked to intrusively investigate those targets that were characteristic of a UXB.  A disposal plan was implemented involving the relevant authorities (including the MoD) to ensure that adequate support procedures were in place should a UXB be found.  Zetica investigated the identified targets under supervision of an Explosive Ordnance Clearance (EOC) Engineer.

A 500kg UXB was uncovered. As a result of the detailed planning, the UXB was disposed of in-situ with minimum disturbance.

 

PIPELINE AND CABLE ROUTES SURVEYED IN A SINGLE SWEEP

Non-intrusive surveys are typically required as part of the pre-construction surveys to inform pipeline and cable route design and planning requirements.  These include non-intrusive surveys for archaeology, existing pipe detection, ground stability, cathodic protection, UXO and many other issues relating to construction.

Using its wide-ranging inhouse capability, ZeticaUXO assessed the various requirements of the surveys and created a towed integrated geophysical survey platform (TOAD) incorporating our data acquisition system (ZDAS).

Pipeline routes could then be surveyed in a single sweep with a range of electromagnetic, magnetic and natural gamma instruments, integrated with GPS, on a single platform.

The results were a single survey that not only provided the location of potential UXO, but also changes in geology, groundwater, location of buried waste, archaeological features, and utility services.

Not only did this negate the requirement to undertake additional separate surveys (therefore saving on survey costs and management time), but by integrating and reporting the datasets together it was possible to provide better interpretation to corroborate the identification of objects, thus adding more value to the surveys.

Investigation Case Histories 5

Investigation Case Histories 8

ZONING THE UXO RISK THROUGH NON-INTRUSIVE SURVEYS

Investigation Case Histories 12

Zetica was asked to provide UXO support services for a site in Kent which a UXO specialist had identified as having a site-wide moderate to high risk of UXO encounter.

A non-intrusive magnetic survey was undertaken to identify ferrous targets that may have been UXO. Specifically, WWI bombs were targeted due to the former use of the site as a WWI bombing range.

Numerous magnetic anomalies were detected by the survey and Zetica’s geophysicists modelled the profiles of individual targets to determine which ones had characteristics similar to the type of UXO anticipated.

Through this discriminatory modelling process, we were able to confidently predict the areas where UXO encounter was most likely and could therefore provide a more accurate zoning of the UXO risk on the site. In particular, we were able to delineate the area used for the WWI bombing practice.

This allowed the client to concentrate their intrusive works in areas with a lower risk category. As a result, ground works began much sooner than was anticipated and a safe, phased development was put in place.